+ | ====== Geothermal electricity cost ====== | ||
+ | Next tables contain the economic parameters that have been introduced in the [[deep_geothermal_more_2|geothermal power plant]] | ||
+ | |||
+ | ^ Specific investment [CHF< | ||
+ | ^ ^2035 ^2050 ^ | ||
+ | ^MIN |5'293 < | ||
+ | ^MID |11' | ||
+ | ^MAX |16' | ||
+ | |||
+ | ^ [[o_m_cost|O& | ||
+ | ^2035 ^2050 ^ | ||
+ | |391 |221 | | ||
+ | |||
+ | *The O&M is considered to be the 3.5% of the investment cost < | ||
+ | |||
+ | ^[[life_time|Lifetime]] [years] |20 < | ||
+ | |||
+ | ===== References ===== | ||
+ | [1] [[http:// | ||
+ | |||
+ | [2] [[http:// | ||