Next tables contain the economic parameters that have been introduced in the Decentralized direct electric heating model.

Specific investment [CHF2010/kWe]
2011-2050
MIN 48 [2]
MID 240 [1][2]
MAX 485 [2]
O&M cost [CHF2010/kWe]
2011-2050
8 [2]
Lifetime [years] 15 [1]

References

[1] NERA & AEA (2009), The UK Supply Curve for Renewable Heat, Study for the Department of Energy and Climate Change.

[2] Commission of the European Communities (2008), Energy Sources, Production Costs and Performance of Technologies for Power Generation, Heating and Transport